No. | Project Name | Project Scale(MW) | Unit Type | Completion Date | Contracting Mode | Acquired Honors |
---|
1 | Zhejiang Beilun Power Plant Phase I Project | 2×600 | Subcritical coal-fired units | Nov, 1994 | EPC |
|
2 | Zhejiang Jiaxing Power Plant Phase I Project | 2×300 | Subcritical coal-fired units | Dec, 1995 | EPC | High Quality Medal |
3 | Zhejiang Taizhou Power Plant Phase IV Project | 2×330 | Subcritical coal-fired units | Jun, 1997 | EPC | High Quality Project |
4 | Zhejiang Shaoxing Qianqing Power Generation Project | 1×125+1×135 | Super High-pressure coal-fired units | Jan, 2000 | EPC | Qianjiang Cup |
5 | Zhejiang Beilun Power Plant Phase II Project | 3×600 | Subcritical coal-fired units | Sept, 2000 | EPC | Luban Medal |
6 | Zhejiang Wenzhou Power Plant Phase II Project | 2×300 | Subcritical coal-fired units | Sept, 2001 | EPC | Silver Medal |
7 | Zhejiang Changxing Power Plant Phase I Project | 2×300 | Subcritical coal-fired units | May, 2003 | EPC | Luban Medal |
8 | Zhejiang Wenzhou Power Plant Phase III Project | 2×300 | Subcritical coal-fired units | July, 2005 | EPC | Silver Medal |
9 | Zhejiang Jiaxing Power Plant Phase II Project | 4×600 | Subcritical coal-fired units | Oct, 2005 | EPC | Luban Medal |
10 | Zhejiang Changxing Power Plant Phase II Project | 2×300 | Subcritical coal-fired units | June, 2006 | EPC |
|
11 | Zhejiang Taizhou Power Plant Phase V Extension Project | 2×300 | Subcritical coal-fired units | April, 2008 | PM |
|
12 | Anhui Fengtai Power Power Plant Phase I Project | 2×600 | Supercritical coal-fired units | Sept, 2008 | PM | Silver Medal |
13 | Zhejiang Beilun Power Plant Phase III Project | 2×1000 | Ultra-supercritical coal-fired units | June, 2009 | PM | Gold Medal |
14 | Zhoushan Langxi Power Plant Phase II Project | 1×300 | Subcritical coal-fired units | Oct, 2010 | General contracting for civil work+PM |
|
15 | Zhejiang Shaoxing Binhai Co-generation Power Plant | 2×300 | Subcritical coal-fired units | Oct, 2011 | PM+ Supervision |
|
16 | Zhejiang Jiaxing Power Plant Phase III Project | 2×1000 | Ultra-supercritical coal-fired units | Oct, 2011 | PM |
|
17 | Zhejiang Zheneng Zhoushan Liuheng Power Plant | 2×1000 | Ultra-supercritical coal-fired units | Sep, 2014 | PM | Year 2014-2015 Gold Medal High Quality |
18 | Fengtai Power Plant Phase II Project | 2×660 | Ultra-supercritical coal-fired units | Dec,2013 | PM |
|
19 | Taizhou No.2 Power Plant | 2×1000 | Ultra-supercritical coal-fired units | Dec, 2015 | PM |
|
20 | Vung Ang I Thermal Power Plant Boiler BOP Project in Vietnam | 2×600 | Subcritical coal-fired units | May, 2015 | Boiler BOP |
|
21 | Duyen Hai I Thermal Power Plant Phase I Project in Vietnam | 2×600 | Subcritical coal-fired units | Jan, 2016 | EPC Management |
|
22 | Wenzhou Power Plant Phase IV Project | 2×660 | Ultra-supercritical coal-fired units | Dec, 2015 | PM |
|
23 | Xinjiang Akesu Textile Industry City Thermal Power Plant Project | 2×350 | Supercritical coal-fired units | Under Construction | General Contracting+PM |
|
24 | Ningxia Zaoquan Power Plant Project | 2×660 | Ultra-supercritical coal-fired units | Dec, 2017 | PM |
|
25 | Zheneng Shaoxing Binhai Thermal Power Plant Phase II Extention Project | 4×50 | Back Pressure Type Unit | Under Construction | EPC
|
|